N. Shallowford at N. Peachtree & Ellwyn Dr. Roundabout Project
Construction Dates
- Stage 1
- The change to the intersection control is a temporary condition to allow construction to begin for the conversion to a roundabout intersection. Stage 1 traffic shift will occur from approximately February 20th to June 1st 2024. Electronic signs will be placed on each approach 10 days prior to February 20th , to warn the general traffic of the intersection control change and when it will be implemented.
- Stage 2
- June 1st to June 28th 2024 (Traffic shift rendering will be provided by May 2024)
- Stage 3
- June 28th to September 2024 (Traffic shift rendering will be provided by May 2024)
- Stage 4
- September 2024 to November 1st 2024 (Traffic shift rendering will be provided by August 2024)
- Approximate Completion Date
- November 15th 2024